Title of Item:DAG Architects
Description/Introduction:

Review current status of Projects:

Navarre High School North Concession Stand

Chumuckla Elementary School Classroom Addition

Douglas A. Dillon Administrative Center

Southend K-8 School

Construction Bids for King Middle School and Milton High School Energy Upgrades

 

Recommendation/Action Requested:

Requesting Board approval for 

Navarre High School North Concession Stand -- Phase III Drawing, Preliminary Opinion of Cost

Chumuckla Elementary Classroom Addition - Change order - Rain Days

Construction Bids:  King Middle School Energy Upgrades and Milton High School Energy Upgrades (Bid tabulations attached)



Financial Impact:
A-Funds required from School Board?No
B-Amount required
C-Grant/Project Synopsis attached?No
D-Date Grant/Project Reviewed/Approved by Accountant:


Legal Review
Does item require legal review?No
If Yes, Approval Date

REVIEWERS:
ReviewerActionDate
Harrell, JoeyApproved2/6/2018 - 4:12 PM
Pattullo, MelanieApproved2/6/2018 - 4:32 PM
ATTACHMENTS:
DescriptionUpload DateType
DAG Architects Recommendations/Status of Projects2/5/2018Cover Memo
Navarre High -Concession Stand- Phase 3 Drawings2/5/2018Backup Material
Navarre High -Concession Stand- Phase 3 Opinion of Costs2/5/2018Backup Material
Chumuckla Elementary - Change Order No. 82/5/2018Backup Material
King Middle School Bid Tabulation2/6/2018Backup Material
Milton High School Bid Tabulation2/6/2018Backup Material