October 24, 2013 Board Meeting
.
I am requesting Board Approval of change orders decreasing the projects payable below to the appropriate contractor by the amounts shown. These decreases are to reflect recent payments made to suppliers and the associated tax savings acquired through direct purchasing. Details are printed on the following spreadsheets.
.
·
Chumuckla Elementary – New Kitchen/Cafeteria/Music/Art Rooms
o
Larry Hall Construction
o
$ 183,305.11
.
·
Dixon Intermediate – Kitchen Expansion/Cafeteria Renovation
o
Larry Hall Construction
o
$ 22,498.81
.
·
Gulf Breeze High – Softball/Baseball Fieldhouses
o
A.E. New, Jr. Inc.
o
$ 169,408.27
.
·
Jay High – Kitchen/Cafeteria/Band/Chorus/Demo Bldg 1
o
R.D. Ward Construction
o
$ 98,859.88
.
·
Milton High – Science Labs
o
A.E. New, Jr.
o
$ 32,247.82