July 21, 2016 Board Meeting
I am requesting Board Approval of change orders decreasing the projects payable below to the appropriate contractor by the amounts shown. These decreases are to reflect recent payments made to suppliers and the associated tax savings acquired through direct purchasing. Details are printed on the attached spreadsheets.
· Gulf Breeze Middle – Kitchen Expansion/Cafeteria Renov
o A.E. New, Jr., Inc.
o $ 2,733.50
· Gulf Breeze High – Chiller Plant Ph III
o A.E. New, Jr., Inc.
o $ 7,838.77
· Holley Navarre Middle – Kitchen Expansion/Cafeteria Renov
o Jack Moore & Co, Inc.
o $ 7,640.71
· Milton High – Chiller /HVAC Renov. & Bldg. 35 Energy Upgrades
o A.E. New, Jr., Inc.
o $-(no change)- Chiller/HVAC
o $ 31,148.15 Bldg. 35 Upgrades