March 13, 2014 Board Meeting
I am requesting Board Approval of change orders decreasing the projects payable below to the appropriate contractor by the amounts shown. These decreases are to reflect recent payments made to suppliers and the associated tax savings acquired through direct purchasing. Details are printed on the following spreadsheets.
Dixon Intermediate – Kitchen Expansion/Cafeteria Renovation
o Larry Hall Construction
o $ 55,005.01
Jay High – Kitchen/Cafeteria/Band/Chorus/Demo Bldg 1
o R.D. Ward Construction
o $ 79,319.81
Milton High – Science Labs
o A.E. New, Jr.
o $15,042.67